WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

DTC Capital City Phase - I

Project Status as on Quarter ending 31-03-2024
Updated as on 06-04-2024

Booking Status

  • Residential Apartments Booked
    390

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    224

  • Mechanical Parking Booked
    132

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - A - 3 1 Under Construction
Block - A - 3 2 Under Construction
Block - A - 3 3 Under Construction
Block - A - 3 4 Under Construction
Block - A - 3 5 Under Construction
Block - A - 3 6 Under Construction
Block - A - 3 7 Under Construction
Block - A - 3 8 Under Construction
Block - A - 3 9 Under Construction
Block - A - 3 10 Under Construction
Block - A - 3 11 Under Construction
Block - A - 3 12 Under Construction
Block - A - 3 13 Under Construction
Block B - 2 1 Under Construction
Block B - 2 2 Under Construction
Block B - 2 3 Under Construction
Block B - 2 4 Under Construction
Block B - 2 5 Under Construction
Block B - 2 6 Under Construction
Block B - 2 7 Under Construction
Block B - 2 8 Under Construction
Block B - 2 9 Under Construction
Block B - 2 10 Under Construction
Block B - 2 11 Under Construction
Block B - 2 12 Under Construction
Block B - 2 13 Under Construction
Block - C - 1 1 Under Construction
Block - C - 1 2 Under Construction
Block - C - 1 3 Under Construction
Block - C - 1 4 Under Construction
Block - C - 1 5 Under Construction
Block - C - 1 6 Under Construction
Block - C - 1 7 Under Construction
Block - C - 1 8 Under Construction
Block - C - 1 9 Under Construction
Block - C - 1 10 Under Construction
Block - C - 1 11 Under Construction
Block - C - 1 12 Under Construction
Block - C - 1 13 Under Construction
Block - D - 10 1 Under Construction
Block - D - 10 2 Under Construction
Block - D - 10 3 Under Construction
Block - D - 10 4 Under Construction
Block - D - 10 5 Under Construction
Block - D - 10 6 Under Construction
Block - D - 10 7 Under Construction
Block - D - 10 8 Under Construction
Block - D - 10 9 Under Construction
Block - D - 10 10 Under Construction
Block - D - 10 11 Under Construction
Block - I - 5 1 Under Construction
Block - I - 5 2 Under Construction
Block - I - 5 3 Under Construction
Block - I - 5 4 Under Construction
Block - I - 5 5 Under Construction
Block - I - 5 6 Under Construction
Block - I - 5 7 Under Construction
Block - I - 5 8 Under Construction
Block - I - 5 9 Under Construction
Block - I - 5 10 Under Construction
Block - I - 5 11 Under Construction
Block - I - 5 12 Under Construction
Block - I - 5 13 Under Construction
Block - J - 4 1 Under Construction
Block - J - 4 2 Under Construction
Block - J - 4 3 Under Construction
Block - J - 4 4 Under Construction
Block - J - 4 5 Under Construction
Block - J - 4 6 Under Construction
Block - J - 4 7 Under Construction
Block - J - 4 8 Under Construction
Block - J - 4 9 Under Construction
Block - J - 4 10 Under Construction
Block - J - 4 11 Under Construction
Block - J - 4 12 Under Construction
Block - J - 4 13 Under Construction

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Lobby
2 Staircase
3 Lift
4 Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download