WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

ELYSIYA

Project Status as on Quarter ending 31-03-2024
Updated as on 16-05-2024

Booking Status

  • Residential Apartments Booked
    33

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    9

  • Mechanical Parking Booked
    5

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block 1 - 2nd to 7TH Floor - Residential 3 Completed Without CC
Block 1 - 2nd to 7TH Floor - Residential 4 Completed Without CC
Block 1 - 2nd to 7TH Floor - Residential 5 Completed Without CC
Block 1 - 2nd to 7TH Floor - Residential 6 Completed Without CC
Block 2 - First Floor- Residential 1 Completed Without CC
Block 1 - Ground & First Floor - Commercial 1 Completed Without CC
BLOCK 1 - First Floor - Residential 1 Completed Without CC
Block 1 - 2nd to 7TH Floor - Residential 2 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 2 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 3 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 4 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 5 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 6 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 7 Under Construction
Block 2- 2nd to 12th Floor - Residential 8 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 9 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 10 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 11 Completed Without CC
Block 2- 2nd to 12th Floor - Residential 12 Completed Without CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Facility
2 Fire Facility
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed Without CC Entrance
2 Completed Without CC Common Area
3 Completed Without CC Lobby
4 Completed Without CC Stairs
5 Completed Without CC Lift
6 Completed Without CC Roof

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download
Other 29-08-2023 29-08-2023 29-09-2023