WEST BENGAL REAL ESTATE REGULATORY AUTHORITY

WBRERA

DESTINY

Project Status as on Quarter ending 30-09-2023
Updated as on 12-12-2023

Booking Status

  • Residential Apartments Booked
    24

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    16

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
Block - 1 1 Completed With CC
Block - 1 2 Completed With CC
Block - 1 3 Completed With CC
Block - 1 4 Completed With CC

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Fire Fighting Facilities

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Completed With CC Power Backup
2 Completed With CC Lift
3 Completed With CC Lobby
4 Completed With CC Roof
5 Completed With CC Septic Tank
6 Completed With CC Underground Water Reservoir
7 Completed With CC Overhead Tank
8 Completed With CC Ground Work

Approval for NOC

Approved Document Approval Applied Approval Expected Approval Received Modifications Download