  • Residential Apartments Booked
    10

  • Commercial Unit Booked
    0

  • Basement Parking Booked
    Not mentioned

  • Covered Car Parking Booked
    8

  • Mechanical Parking Booked
    Not mentioned

Status of construction of each building/floor with photographs

Block/Building Floor Construction Status Download
TOWER E; RESIDENTIAL B+G+13 1 Not Started
TOWER E; RESIDENTIAL B+G+13 2 Not Started
TOWER E; RESIDENTIAL B+G+13 3 Not Started
TOWER E; RESIDENTIAL B+G+13 4 Not Started
TOWER E; RESIDENTIAL B+G+13 5 Not Started
TOWER E; RESIDENTIAL B+G+13 6 Not Started
TOWER E; RESIDENTIAL B+G+13 7 Not Started
TOWER E; RESIDENTIAL B+G+13 8 Not Started
TOWER E; RESIDENTIAL B+G+13 9 Not Started
TOWER E; RESIDENTIAL B+G+13 10 Not Started
TOWER E; RESIDENTIAL B+G+13 11 Not Started
TOWER E; RESIDENTIAL B+G+13 12 Not Started
TOWER E; RESIDENTIAL B+G+13 13 Not Started
TOWER E; RESIDENTIAL B+G+13 14 Not Started
TOWER E; RESIDENTIAL B+G+13 15 Not Started
TOWER F; RESIDENTIAL B+G+13 1 Not Started
TOWER F; RESIDENTIAL B+G+13 2 Not Started
TOWER F; RESIDENTIAL B+G+13 3 Not Started
TOWER F; RESIDENTIAL B+G+13 4 Not Started
TOWER F; RESIDENTIAL B+G+13 5 Not Started
TOWER F; RESIDENTIAL B+G+13 6 Not Started
TOWER F; RESIDENTIAL B+G+13 7 Not Started
TOWER F; RESIDENTIAL B+G+13 8 Not Started
TOWER F; RESIDENTIAL B+G+13 9 Not Started
TOWER F; RESIDENTIAL B+G+13 10 Not Started
TOWER F; RESIDENTIAL B+G+13 11 Not Started
TOWER F; RESIDENTIAL B+G+13 12 Not Started
TOWER F; RESIDENTIAL B+G+13 13 Not Started
TOWER G; RESIDENTIAL B+G+13 1 Not Started
TOWER G; RESIDENTIAL B+G+13 2 Not Started
TOWER G; RESIDENTIAL B+G+13 3 Not Started
TOWER G; RESIDENTIAL B+G+13 4 Not Started
TOWER G; RESIDENTIAL B+G+13 5 Not Started
TOWER G; RESIDENTIAL B+G+13 6 Not Started
TOWER G; RESIDENTIAL B+G+13 7 Not Started
TOWER G; RESIDENTIAL B+G+13 8 Not Started
TOWER G; RESIDENTIAL B+G+13 9 Not Started
TOWER G; RESIDENTIAL B+G+13 10 Not Started
TOWER G; RESIDENTIAL B+G+13 11 Not Started
TOWER G; RESIDENTIAL B+G+13 12 Not Started
TOWER G; RESIDENTIAL B+G+13 13 Not Started
TOWER H; COMMERCIAL G+2 1 Not Started
TOWER H; COMMERCIAL G+2 2 Not Started
TOWER H; COMMERCIAL G+2 3 Not Started
TOWER H; RESIDENTIAL B+G+13 1 Not Started
TOWER H; RESIDENTIAL B+G+13 2 Not Started
TOWER H; RESIDENTIAL B+G+13 3 Not Started
TOWER H; RESIDENTIAL B+G+13 4 Not Started
TOWER H; RESIDENTIAL B+G+13 5 Not Started
TOWER H; RESIDENTIAL B+G+13 6 Not Started
TOWER H; RESIDENTIAL B+G+13 7 Not Started
TOWER H; RESIDENTIAL B+G+13 8 Not Started
TOWER H; RESIDENTIAL B+G+13 9 Not Started
TOWER H; RESIDENTIAL B+G+13 10 Not Started
TOWER H; RESIDENTIAL B+G+13 11 Not Started
TOWER H; RESIDENTIAL B+G+13 12 Not Started
TOWER H; RESIDENTIAL B+G+13 13 Not Started
TOWER J; COMMERCIAL G+2 1 Not Started
TOWER J; COMMERCIAL G+2 2 Not Started
TOWER J; COMMERCIAL G+2 3 Not Started
TOWER J; RESIDENTIAL B+G+13 1 Not Started
TOWER J; RESIDENTIAL B+G+13 2 Not Started
TOWER J; RESIDENTIAL B+G+13 3 Not Started
TOWER J; RESIDENTIAL B+G+13 4 Not Started
TOWER J; RESIDENTIAL B+G+13 5 Not Started
TOWER J; RESIDENTIAL B+G+13 6 Not Started
TOWER J; RESIDENTIAL B+G+13 7 Not Started
TOWER J; RESIDENTIAL B+G+13 8 Not Started
TOWER J; RESIDENTIAL B+G+13 9 Not Started
TOWER J; RESIDENTIAL B+G+13 10 Not Started
TOWER J; RESIDENTIAL B+G+13 11 Not Started
TOWER J; RESIDENTIAL B+G+13 12 Not Started
TOWER J; RESIDENTIAL B+G+13 13 Not Started

Status of Construction of Internal Infrastructure with photographs

Sl No. Title Download
1 Water Supply
2 Fire Extinguisher
3 Emergency Evacuation

Status of Construction of Common Areas with photographs

Sl No. Construction Status Description Download
1 Under Construction Lobby
2 Under Construction Stairs
3 Not Started Lift
4 Not Started Roof

Approval for NOC